What goes on a CoC test sheet

The test report behind a Certificate of Compliance, in the order you do it, with the value each test has to make and the clause that sets it. The sheet is only half the job; the other half is the installation being right before you start.

The tests, one by one

Clause numbers are from SANS 10142-1 Ed 3.3 (public-enquiry draft). The licensed Ed 3.3 book is the authority, and the ECB's test report template is the form most SA sparkies hand in.

01Continuity of bonding≤ 0,2 Ω

Tested with a supply of 4–24 V and 0,2 A or more. Every extraneous conductive part that has to be bonded, checked back to the earth bar. 8.6.2.

02Earth continuity conductorby device rating

DB earth terminal to the earthing terminal of every point of consumption and switch. Sockets tested with a plug inserted so the earth pin counts. 6 A allows 1,533 Ω, 63 A allows 0,146 Ω. Full table here. 8.6.3.

03Continuity of ring circuitswhere applicable

Both ends of each live conductor removed, separated, tested for continuity, then reconnected to the same terminal. A ring that "works" can still be two radials. 8.6.4.

04Earth and neutral loop impedancetrips in time

Measured at the main switch. The fault current must reach at least 3× the rated current of the device up to 63 A, and above 63 A the disconnection time must not exceed 5 s. Record the reading. 8.6.5.

05Elevated voltage on the supply neutralnotify > 25 V

Main switch off, measure the supply neutral against an earth external to the installation (a spike driven into wet ground is allowed as the reference). 0 to 25 V: notify the user or lessor. Above 25 V: notify the supplier and the user. Above 50 V: disconnect the installation and notify the supplier. 8.6.6.

Older testing guides (ECB, Edition 3) list only the 25 V and 50 V steps. Edition 3.3 (Amdt 3) adds the 0–25 V line.

06Earth resistance at the electrodeper SANS 10199

8.6.7 sets no ohm value of its own: earth resistance is determined to SANS 10199, or with an appropriate instrument. Where the supplier provides an earthing terminal (TN) the test is optional (8.6.7.2). Where there is no earthing terminal or an alternative supply is installed, it is how you confirm the earthing system. Electrode calculator here.

07Insulation resistance≥ 1,0 MΩ

Test voltage at least twice nominal, minimum 500 V, with dimmers, EL units, SPDs and other electronics disconnected. Sub-boards may be split, but each section still has to make 1,0 MΩ. Details here. 8.6.8.

08Voltage at the DB, no load and on loadwithin limits

All load off, then maximum available load on, measured at the point of control. Outside the standard voltage limits (5.4.2) the supplier gets notified. 8.6.9, 8.6.10.

09Earth leakage operationhold at 50%, trip at 100%

Measured at the outlets, on each phase conductor of the outlet, and the tripping current recorded on the report. Every unit in the DB gets its own test. Then the test button, to prove the mechanism (8.6.12 is a function check, not a sensitivity test). 8.6.11.

The sheet does not make an installation compliant. A CoC is issued by a registered person under the Electrical Installation Regulations, 2009, for the installation as found. Readings that pass do not fix a bad joint, a borrowed neutral or a circuit with no earth at all. If the installation is not compliant, the honest answer is a list of defects, not a form with numbers in every block.

What the paperwork has to carry

Annexure 1 of SANS 10142-1 is the test report layout; the ECB publishes its own template around the same tests. A CoC built on a test report nobody can read is a dispute waiting for a sale to fall through.

The part nobody warns you about

The testing is the clean half of a CoC job. The other half is paperwork: readings written down as you go, a report that survives a bank or a buyer looking at it, an invoice that gets paid. That is the part that eats your evening and the part that gets you called back.